How to generate PR containing multi-line items in MRP run?

Question: Dear SAPfans,

In our company, our planner want PR generated by MRP containing many items for the same vendor. in my knowledge, it's not possbile,
any solutions on this?

Anthony

Answer:
k,
I only know that we can maintain the outline agreements then run the MRP to create the schedule line for them. Use the feature maybe can solve your problem. Just like you said, one PR multiple items is impossible.

Answer:
Jie,

You method is very useful for these vendors which have good releationsip and long-term purchasing agreement with my company.
In my company, the vendor is almost fixed. i will consider the purchasing price situation to make solution. thanks to your reply.

My MSN: dk_deng@hotmail.com


Kui

Answer:
Hi Jackey,

I only know that we can maintain the outline agreements then run the MRP to create the schedule line for them.
Just a minor correction that this is not the case of Outline Agreement but Scheduling Agreement since in regard to Outline Agreement, the PRs will be generated during planning run which will, then, be converted into Release Order. In regard to the case of Scheduling Agreement, with further setting in Source List as MRP relevant (with selection parameter '2' to be entered in MRP field of Source Record), the planning run will generate directly the SA Delivery Schedule Line Item. Neither PR nor PO document is generated in this particular case.

Hi Anthony,

In our company, our planner want PR generated by MRP containing many items for the same vendor. in my knowledge, it's not possbile,
No, it is true that you can not generate multiple-line item PRs during planning run (for the case of stock items from Work Orders) and this is the standard feature of SAP. However, it is not clear to me why you would like to create such multiple-line item PRs during planning run. Any specific business reason?

Cheers,
HT
_________________
Moderator:

Answer:
Dear HT,

The reason is very simple, our planner don't want so many PRs generated, if the vendor is the same, all lines should be combined to one PR, otherwise, during PO creation with reference to PR, our planner should to find which items is linked to the same vendor, then convert them to one PO. this will increase their effort.

Thanks to your support.

Anthony

Answer:
Dear HT,
You are right, I just didn't say the detail setting.

Answer:
Hi Anthony,

It is true to say that this can be well covered in MM module. What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.

Cheers,
HT
_________________
Moderator:

Answer:
Hi Anthony,

It is true to say that this can be well covered in MM module. What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.

Cheers,
HT
_________________
Moderator:

Answer:
Hi Anthony,

It is true to say that this can be well covered in MM module. What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.

Cheers,
HT
_________________
Moderator:

Answer:
Hi Anthony,

It is true to say that this can be well covered in MM module. What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.

Cheers,
HT
_________________
Moderator:

Answer:
Hi Anthony,

It is true to say that this can be well covered in MM module. What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.

Cheers,
HT
_________________
Moderator:

Answer:
Dear HT,

Just now i have tested, the result is fine with auto. PO creation. thank...

Anthony