Question:
Hi All
We use repetitive manufacturing and the last operation is performed at the external vendor ..
Is it possible to use externally processed operation in repetitive manufacturing ?
If possible, pl let me know the setup required..
thanks for your time
RK27
Answer:
I don't think this is possible in Repetitive manufacturing.
Alternatively, you can use subcontract PO (material with procurement type F, special procurement type 30) instead of external processing.