Question:
Hi
I have a situation as new operations are added to Production order in change mode. These operations are relevant for costing only, such operations don’t need operations confirmation and hence there won’t be any actual cost.
For the above scenario need to get planned cost to be displayed based on the hours we input for each activity. Is there any way to implement the above requirements?
Please some one can help me in this regard as it is very urgent.
Answer:
1. Add the operations you want in change mode as last operations with costing relavent control key.
2. Confirm the operations which you want to confirm.
3. Dont confirm the operations which you dont need actual costing.
4. Do TECO for the order.
Hope this will solve your problem.