Question:
Dear all,
In my production order , i hv one externally processed operation. i hv assigned control key pp02 to it.
Now i convert this PR to subcontracting PO. Now even if i am not issuing raw material to vendor & not doing MIGO. System is allowing me to 'confirm' that operation thru CO11n.
My requirement is that system should not allow me to confirm that operation unless MIGO of that subcontracting PO is over. How to make that setting for 'this check?'
Thks in advance
Answer:
Still waiting for some input?
Thks
Answer:
There is no standard setting in the system which allows you to prevent confirma tion if the MIGo is not done but there is a setting in Selection profile in the configuration where you can define user stauses & the priority. Then system will read the order status & if there is no MIGO, it will give error / warning message depending upon your settings.
ashua_81.
Answer:
Thanks Ashua_81
Can u pls tell me detailed steps ( t.code wise ) for doing this setting?
Thks in adv.
Answer:
hi,
i'm already searching a solution to this problem, system allows me to confirm the production order what should i do? how will i use selection profiles or how did u solve this problem please help me.
thanks.
Answer:
Hi ashua,
Pls let me know detailed process for configuring it.
Thanks in advance,