Field "Next Inspection Date" in Material Batch

Question: Hi all,

Is anyone use the field "Next Inspection Date" in Material Batch ? How to use this field and what is the purpose ?

Thanks in advance.

Nelson.

Answer:
check: http://help.sap.com/saphelp_46c/helpdata/en/be/00bbcfca5311d2961800a0c930e04c/content.htm

hope it helps.
dp

Answer:
This is the date the sytem calculates to restest material that is in storage. You need to set an inspection interval and activate the recurring inspection type in the material master. Once that is done you can set up a job to run automatically or it can be run manually.

The date is calculated from the inspection interval entered in the material master and the manufacture date.

Hope this helps.

Chris

Answer:
Thank Daniel & Chris.

Regards
Nelson