Question: Hi friends,
I am facing a problem .

The process chain has failed giving me an error as :Process LOADING,
variant ZPAK_5PN1XMCA800XJQN4OZ9VO4PS1
is not scheduled waiting for event RSPROCESS 6IZ5JP92HQGVX4TD8W7R6U7CA .

Diagnosis

Process LOADING (variant ZPAK_5PN1XMCA800XJQN4OZ9VO4PS1 ) needs to be
started. According to the process chain maintenance, it needs to be
scheduled while waiting for event ZPAK_5PN1XMCA800XJQN4OZ9VO4PS1
6IZ5JP92HQGVX4TD8W7R6U7CA . However, this is not the case.

System response

The chain is cancelled.


What does this error mean. can anybody explain why am i getting such an error.


Has anyone faced such a problem. Can I get the answer as soon as possible.Its urgent .

Regards,

spg17

Answer:
Hi,

The process chain has not trigger with event.You have to trigger the event for thr process chain.

Procedure:-
If your process chain triggering with specific date and time.
Set the date & time in maintain variant and schedule it according to your requirement and save it and schedule and activate the process chain.
Goto process cahin-->right click on start process-->got to maintain variant-->Pick the event there.
and goto SM64 --GIVE event name over there then trigger the button.

Hence your process chain will run.
_________________
Prasad

Answer:
Hi Prasad,

thanks for your answer but this all is in place.
I have defined all of this.
the process chain runs after a job in r/3
triggers an event in BW which subsequently
causes the process chain to run.

Please do respond.