Question:
On several tasks in our workflow I have unchecked the "Confirm end of processing" button in the task and them in the Workflow templete unselected the Confirm end of processing in the Task Properties. This change works in our Test system, however when this change is transported to QA, the boxes are not checked but we are still receiving the "Complete Work Item" pop-up to complete the task. The transport did not have any errors. How can I get this work in our QA box like it works in DEV? Thanks.
Answer:
Hi,
If you transport a WF template, a new version is created.
All active workitems in the inbox should still have the old version.
In the workflow log you can check if it has anything to do with versions.
Plus sometimes you have to refresh the buffers, to update hrs1205 after transport. try transaction SWU_OBUF.
Regards, Rob Dielemans