Fill aggregates in parallel

Question: Hello all,

I’m new in BW and I have the following easy doubt:

“Last week we activated some aggregates but we noticed that it takes long time to fill it. For each cube we have approximately 3 or 4 aggregates.

It is possible to fill this aggregates in parallel? We notice that the system only use one process and takes so many time (more than 1 hour).


Thanks in advance,
Charles

Answer:
Yes you can do the initial fill of the aggregates in parallel. However, subsequent rollups can't.