Question:
Hello all,
I’m new in BW and I have the following easy doubt:
“Last week we activated some aggregates but we noticed that it takes long time to fill it. For each cube we have approximately 3 or 4 aggregates.
It is possible to fill this aggregates in parallel? We notice that the system only use one process and takes so many time (more than 1 hour).
Thanks in advance,
Charles
Answer:
Yes you can do the initial fill of the aggregates in parallel. However, subsequent rollups can't.