Question:
Hi Gurus
Sorry about this question.
I had look for around this forum, but I can not found a solution to my problem.
I have scheduled a prcess chain invloved a ODS and further process to a cube. The problem is with deltas from ODS, they remain in yellow forever. But if I do actualization manually it runs Ok.
do I missing soemthing? please I am lost ... any Idea?
Thx in advance ..
Sergio
Answer:
Prior to loading data from your ODS to your cube you need to activate your ODS data in your process chain. This does not happen automatically from the ODS load process in your PC if you have the ODS not set to automatically activate.
Add the Activate ODS process to your PC prior to running a delta to the cube and you should be OK.
- Stephen
_________________
As a rule I don't answer Questions in PM.
(this is not to be a d**k, but it is to allow everyone to benefit from information. Not just one person.) Ask a question in the forum and I will answer it if I can.
Answer:
Thx SBobcat for you reply....
I have an activation process in my ODS and works fine, the problem is the next step. The cube actualizacion starts and never ends.
Any idea?
Thx.