I encountering errors trying to setup a process chain for the following:
In RSPC, I've created a Process Chain to execute an infopackage to load an ODS object. Upon a successful ODS load I will execute another infopackage to load an infocube from the updated ODS. When I do a check on the Process Chain, an error comes back informing me that I cannot have the proceeded "ODS Further update" prior to executing the infopackage to load the infocube from the ODS.
Is it possible to setup a Process Chain to execute and ODS load and subsequently load the infocube from a successful ODS load.
ZMAN
Answer:
you can do it.
1. Did you activated ODS in the process chain
2.If you didn't activate do active and proceed futher step
3.Arrow down to successfull