Question: Hi Team

Can any one list out what are the steps to be tested both on r/3 and bw and SEM side after the plug in upgare in R/3 for BW. We are going from 2002.1 to 2003.1.

Please help.

Thnaks in advance.

Best Regards
Neelu

Answer:
Hi Neelu,

Speaking only for the BW side:

-Restore/activate source system (this replicates all datasources)
-Regenerate all transfer rules. If this step shows up any inconsistencies, then there is a program to repair it, forget the name, ZT... something.

Remeber also to stop all V3 collective updates before the upgrade (after dealing with all the delta queues) and to resume them after all checks in R/3 and BW.