Question:
After 2 R3 shutdowns in very short time because of an wrong R3 job. two of our Datasources donīt deliver data anymore.
(R3 4.6; BW 3.1; Plugin 2003.1 ) Datasources Sales and Billing. Looks like V3 is collecting ok but it is not delivered to the Delta Queue anymore. All other DS for this cube are still running ok.
Does somebody can help me??
Answer:
Have you tried actually running the delta from BW?
We too had a restore from a backup after a wrong table drop, and all scheduled deltas were giving an error message about last delta still running or not ok, etc. I just went ahead and ran them one by one manually, and they ran ok (inspite of RSA7 showing 0 or not changing), and after that I rescheduled them.
_________________
Keep smiling
Answer:
Yes I have!
What is very bad is that I can see that V3 is collecting allready about 170000 lines. But there is no way to bring them to the delta queue...
So every delta is going on green without with 0.
Answer:
Take it up immediately with SAP (OSS message with 'Very High' priority, tell them that your sales planners & schedulers dependend on BW reports).
_________________
Keep smiling
Answer:
Try This OSS note 597637, May relate to your issues!
Good luck.
YenCee
Answer:
euh don't panic... how about rescheduling the "job control"???
Answer:
380078 Note suggests below
It is most likely that a delta initialization had not yet run or that the the delta initialization was not successful. A successful delta initialization (the corresponding request must have QM status 'green' in the BW System) is a prerequisite for the application data being written in the delta queue
_________________
Chetan
@ CP...
Answer:
It is most likely that a delta initialization had not yet run or that the the delta initialization was not successful.
He had an operational extraction flow set-up with delta's so i don't think this is will be the case.
Rescheduling the "job control".
I set my money on El's suggestion !
Answer:
EL,TFR
How do u rechedule the JOB Control
what r the steps??
Answer:
/NLBWE > on application 11 (and 13) cleck on job control and schedule a weekly/daily/hourly job from there