Question:
Dear workflow experts,
Do you have any tips on how to balance/distribute servers' workload during massive triggering of events ? Currently I need to trigger more or less 15,000 events in one go for data correction. The events will be triggered from ABAP reports ?
Currently I've set the event processing in SWEQADM to 'Parallel on Server Group', however seems to me that this SWEQADM change did not load-balance the workflows across servers.
Many thanks before for your help.
Rgds,
Paijo
Answer:
one of the possible options is to switch event queue on, this will improve the performance quite a bit.