Question:
Hello GURUS,
My process chain fails and i get deadlock.
I am running subchains in parallel.
BW3.1C
Thanks
BWPC
Answer:
bwpc,
Note that a higher degree of parallel processing and therefore more batch processes only make sense if the system has sufficient capacity (CPUs). You must use approximately one CPU per batch task.
Hope it helps
@C h E t A n...
Answer:
Thanks CHETAN
SOMUCH for ur spontaneous response
How do i solve this problem??
BWPC
Answer:
bwpc,
Make sure that there are enough background processes in the system.
If the minimum requirement cannot be met, I recommend that you adjust the chain to reduce the number of parallel subchains.
@C h E t A n...
Answer:
CHETAN,
u have any NOTES or documents for this,would appreciate that.
BWPC
Answer:
NOTE : 621400
Now pliz dont ask me after seeing NOTE that how do i do that,u need strong BASIS guy or lemme know if u have any VACANCIES for BASIS JOB
@C h E t A n...
Answer:
Thanks SO MUCH CHETAN again
APPRECIATE THAT would try my self with BASIS
defintely would LUV to have u here but u r in INDIA and m at
NEW YORK.
Thanks
BWPC