Question:
We have set SAP up to send a DESADV Idoc out to Business Connector whenever an inbound or outbound delivery is created in SAP. (The Idoc is eventually going to a 3rd party warehouse system to be processed).
Does anyone know how to set up SAP so that a new new Idoc is created for any changes done to the inbound delivery in SAP?
Change pointers only work on master data, and there doesn't seem to be any config table to define change relevant fields (like there is in MM for the PO)!!
Thanks in advance.
Answer:
I don't know about deliveries but for sales order, refer to note 395569.
There may be a similar solution for deliveries.
On the other hand, if you use the SAP decentralized warehouse scenario and if your version is bigger than 4.7, SAP is handling this for you.
_________________
Remi
Answer:
Thanks...unfortunately we on 46c! Anyway, the OSS note was useful...have managed to get delivery changes created by adding a form in MV50AFZZas it says.
Cheers.