Question: Folks,

We have setup an SNP planning book in SNP. The optimizer is running every night and creating planned orders in the manufacturing plants as well as stock transfer requests from the manufacturing plants to the DC. The latter is a problem since these stock transfers are also craeted during the weekend and this should not happen. I believe this is a calendar issue but I have no idea where to look in order to fix this.

Any idea's

Tks

Answer:
Folks,

It is resolved. You can find the calendars in the location master data.