Question:
In the detailed view of SNP interactive planning, component
product name is shown (It shows input product instead of the
output product) for Production Planned (Subcontract) key figure.
This happens only for the products displayed at subcontracting
locations (vendors). Though quantity planned is correctly
calculated and the right PPM as the source of supply is being
displayed without any error.
Plan at the Subcontracting Vendor
Mat# A is the Output product
Mat# b is the Input product
Mat # c is the Input product
A=b+c
Product A at subcontracting location in the SNP interactive
planning, when we look at the production planned key figure
details, the planned order has just one input component(b).
What we expect is either the Finished Part(A)or both the input
components(b,C)
Is there some kind of setting so that we can achieve the above?
Answer:
967120 Wrong Product name in Dependent demand
931851 Wrong plan number in the deteil view.
963546 Production in another location with SNP-PDS/PPM
943887 Detail view: display location for cross systems orders
By implementing the notes, the problem can be solved