Question:
Hi,
I am sending the purchase order from APO to R/3. When I transfer the data through CIF and see the curresponding entries in stock requirement list in R/3, purchase order is 1 day earlier than in SCM.
However, when this purchase order is CIFed back to SCM, date appears correct in SCM ( as what it was before). Is this something because of timezone that difference in date appears in SCM and R/3.
Can someone who came across date issues for transaction data transfer between SCM and R/3 elaborate in more detail please.
Thanks,
Sanjay
Answer:
Most likely it's the time zone issue. Could you confirm the time zones in APO location master and R/3 plant?