Question:
I have the following problem: The sales order created in R/3 are not transferred to APO even if there is an active integration model.
When I look at the transaction "CIF compare and reconcile" I can see my sales order and I can process them manually.
Can somebody explain me why the data are not automatically transferred ??
Thanks for your help
JMB
Answer:
First of all have you put X0 in mrp type of material master?
Is sales order given in plant or mrp area?
Answer:
The MRP Type of X0 makes absolutely no difference in the transfer of data between R/3 and APO, it merely prevents MRP from planning the product further as this is marked as "Externally Planned".
Is the data transfer issue true of all sales orders or just certain ones ?
Regards
Parksy
Answer:
Is there any Queue entry for the sales order?
Answer:
Availability Check set to individual requirements?
Answer:
Hi,
Check the schedule line category in the line item ....are the requirements meant to be transferred for planning.If it is not meant for planning the sales orders wont be transferred to APO....
Ram