Bid closing date - SRM 5.0

Question: Hi ,

In standard bidding process in SRM , whether the company can view or process the bids before the bid closing date.

Request the comments from the forum....

Regards
Mani

Answer:
Hi Mani,

Technically it is possible to view and process the bids before the bid closing date.

In case there are restrictions required then you may need to set up a BAdI to disable ( Viewing would still be possible) selection of bids before the final submission date.

Regards
Gopi

Answer:
Thanks a lot Gopi