SNP Heuristics Not planning the Production.

Question: Hi all,

SNP Heuristics in not generating any SNP planned orders for a material which is produced in house if the PPM(SNP ) is assigned to the active model.

The system generates planned orders if the PPM is deactivated or removed from the model.

Thx in advance for the help.
regards,
Reddy

vcreddy@yahoo.com

Answer:
sound like a bad ppm. do a consistency check on the ppm. make sure its active