APO orders don't go to new resources

Question: Hi,
I could use some help. The guys from master data team created new workcenters. I ciffed them to APO, added data like capacity profile, planner, sort string, etc. I did a LC check, and is okay. I have them in the DS board.
The materials got the new work centers in the routings, in R/3. The RTO's are daily ciffed to APO, in this case without DC, because no BOM change. When I now re-explode the existing scheduled orders, that are on the old resource, I loose the BOM and routing in APO, so they disappear from DS board. The orders only contain a handling activity time - for GR - that is on the current handling resource, that was not touched.

Being new on this forum, and 'green' in APO, I would appriciate feedback.

Thanks a lot.

Answer:
never mind, I found it myself.
FYI: I had to do an initial transfer of the RTO ( with curto_create ). Our CIF job overnight didn't detect the routing changes.