I have a std qst on forecast consumption

Question: we are using DP to run forecast and relase to SNP/PPDS in 1/18 months respectivly.We have also sales orders created from time to time .Which strategy to use in Product master(demand ) where sales orders to consume forecast on same bucket in SNP.
Thanks
Alice,
CGY,PARIS

Answer:
Hi,

You need to set "Strategy" 20 to sales order consume the forecast.

All the best

Arul

Answer:
Thanks a lot!
Alice