Question:
Hi all
I m getting one worning message saying that wrorkcenter/resource is not APO relevant while creating intergration model
can anybody put light on this
Thanks in advance
_________________
Harish Bhangale
SAP PP Consultant
Answer:
Hi there
while transmission of PPM every operation of routing is checked.
If a workcenter does not have a control key which shows, that it is
relevant both for capacity planning and sheduling, and both formulars
are maintained in the workcenter to calculate kapacity demand and sheduling time, the system tells you that it is not relevant for apo.
regards
Klaus