Question: Hello Champions,

I am using CTM functionality of SNP to do supply chain planning. I take a CTM run, say on 17.6.2005. While seeing the orders for the products, I see that the receipts are planned from 3.7.2005 onwards, i.e. if the demand is on 3.7.2005, the recipts would be planned.

If I take the run on 16.6.2005, the receipts would be planned from 2.7.2005 onwards.

Any demand element which is in between the planning run date + 16 days is not planned and is shown as a backlog in the interactive screen.

Any idea about why this is happening? SNP production horizon is 0 days. PP/DS horizon is 30 days.

Akhil

Answer:
what has been set as forecast horizon in SNP 2 tab for that product ??

Answer:
Well, Forecast horizon was set as 0. Anyways, I myself have resolved the problem.

Thanks

Answer:
Pl. share with me also how you actually resolved the problem