APO Planning Time Fence

Question: Hi to everyone!

Could anyone help me, how to set Planning Time Fence in APO.


Hoping for all of your replies.


Thank you very much


Best Regards,

Jet

Answer:
The planning time fence in R/3 (MRP views) becomes the PP/DS fixing period in APO. This period is protected from heuristics in APO although this only prevents orders being created that finish within this period. Orders can start within this period so long as they finish outside of it. This usually confuses people the first time they see this.

Mark W