data transfer to R/3 from APO.

Question: Hello,

I need to transfer PIR from r/3 to APO. This is a test connection to the new our system. It is going to a different system but not to the system which. how do i specify the new system for which the data has to be transferred.

Answer:
go to
SPRO=>APO=> basis settings=>Assign Logical System and Queue type
and see if the system you want is set there.. else create
make sure the r3flag is set X and the inbound and outbound queues are also set up

then go to publications settings and maintain/generate for PIR for each of your locations and see if the logical system is right there too

hope that helps

Answer:
wasnt logged in when i posted the above reply. just in case you want to get back

Answer:
Thanks Harish it worked fine