I have a scenario, where I have to upload data in DP planning book from a legacy system. Can I know where can I find the PUPDATE field in APO, to specify the nature of Update type for DP planning book? The different options available regarding the update type from this field are :
OW1 - Overwrite Completely, First Period distribution
OW2 - Overwrite Completely, Consistent distribution
PW1 - First: Overwrite partially Period Distribution
PW2 - Overwrite partially : Consistent Distribution
DL1 - Delta Update : First Period Distribution
DL2 - Delta Update : Consistent Distribution
Any thoughts onto this would be appreciated.
Regards,
Akhil
Answer:
Akhil,
This is a very interesting question please contact me directly by my user name on this forum.
George
Answer:
Akhil,
So let me know the PUPDATE field in APO type if you happen to know the details. Even I am looking for the same information
Rgds,
Mani
Answer:
I need the answer of the question u hav put here.
Can u pls revert back
Answer:
Try this:
Change this template: /SAPAPO/TS_PSTRU_SAMPLE_MD_GEN in order to load with zeros.
Use the flag [X] Ignore zero values
Update values in table: RSSGTPCLA
This is a non-standard solution but maybe somebody could improve my suggestion.
Yours Faithfully