Model Consistency Check

Question: Hi folks,

When i perform model consistency check it gives following error:

" Conversion of ST to EA for product 300001000 not maintained in master data
Message no. /SAPAPO/SNP 139

Diagnosis
An invalid conversion factor was determined when converting the units for product 300001000 from ST to EA.

System Response
Product 300001000 is not planned.

Procedure
In the product master data, define a rule for converting units from ST to EA."

But i don't find any unit such as 'ST' i am using.

Could anyone provide some clues in avoiding this?

regards,
mns

Answer:
Hello,

I'm afraid I can't really help you with your error message but "ST" is the German abbreviation for "PC".

Hopefully this helps you narrow down your problem.

pld

Answer:
Hi

Your hint was really helpful and i have maintained the conversion as 1PC = 1 EA which is base unit of measure for my product and thus the problem solved.

Many thanks,

regards,
mns