SNP location heuristic planning does not respect lead time

Question: I have a demand that is due on Sept 17. Ran SNP location heuristics and the output states that the demand can be on time.
This is not possible as there is a lead time of 5 days and there is no stock.

Any suggestion on how to trouble-shoot? Thanks.

Answer:
Are you sure that you maintained the lead time in the procurement view in the product master?

Answer:
Yes, the lead time is maintained in the procurment tab of product master.

Answer:
Yes, the lead time is maintained in the procurment tab of product master.

Hi Winnie,

Check on the transportation lanes...

JPAPO

Answer:
There is no transportation lane setup for input material since we don't have vendors in our model.

Material lead time is 10 days.
The mfg lead time is 5 days.

All manufacturing is done in one location.

Thanks for all the suggestion.

Answer:
Hi any update on this as I cannot able to understand why this has happened
Thanks

Answer:
Hi,

Would like to know when did u actually ran the heuristics.

Answer:
Hi,

Would like to know when did u actually ran the heuristics.

Answer:
Hi,

Please let me know the foll things.

1. Is there any Transportation lane maintained in APO. If not, have you transferred Purchasing Info Record from R/3 to APO?

2. What is the source location heuristic identifies for the demand to be met?

3. When did u actually run the heuristics?

Regards,

Akhil

Answer:
1. Is there any Transportation lane maintained in APO. If not, have you transferred Purchasing Info Record from R/3 to APO?

Yes.

2. What is the source location heuristic identifies for the demand to be met?

The manufacturing plant.

3. When did u actually run the heuristics?

Two days before demand is due.