Question:
I have a demand that is due on Sept 17. Ran SNP location heuristics and the output states that the demand can be on time.
This is not possible as there is a lead time of 5 days and there is no stock.
Any suggestion on how to trouble-shoot? Thanks.
Answer:
Are you sure that you maintained the lead time in the procurement view in the product master?
Answer:
Yes, the lead time is maintained in the procurment tab of product master.
Answer:
Yes, the lead time is maintained in the procurment tab of product master.
Hi Winnie,
Check on the transportation lanes...
JPAPO
Answer:
There is no transportation lane setup for input material since we don't have vendors in our model.
Material lead time is 10 days.
The mfg lead time is 5 days.
All manufacturing is done in one location.
Thanks for all the suggestion.
Answer:
Hi any update on this as I cannot able to understand why this has happened
Thanks
Answer:
Hi,
Would like to know when did u actually ran the heuristics.
Answer:
Hi,
Would like to know when did u actually ran the heuristics.
Answer:
Hi,
Please let me know the foll things.
1. Is there any Transportation lane maintained in APO. If not, have you transferred Purchasing Info Record from R/3 to APO?
2. What is the source location heuristic identifies for the demand to be met?
3. When did u actually run the heuristics?
Regards,
Akhil
Answer:
1. Is there any Transportation lane maintained in APO. If not, have you transferred Purchasing Info Record from R/3 to APO?
Yes.
2. What is the source location heuristic identifies for the demand to be met?
The manufacturing plant.
3. When did u actually run the heuristics?
Two days before demand is due.